Time Line is Accurate As Of May 21, 2007 1200h

Campus Map Project Time Line Summer 2007

Goals can either be:

Compleated: Goal is compleated and documented.
Open: The Goal is still being worked on, but is not late.
PastDue: The Goal is still being worked on and is late.
Disc: This Goal was discontinued and a report of why is avaliabe under the reference section for that goal.
Exten: This Goal was extended from it's previous time, it is still being worked on and is not late.  An explination is avaliable under reference.
Prep: This is a preposal that has not passed a group vote and may be for a future team to impliment.

Start and End Date Goal/Status

May 21

to Aug 6

Goal Start Date Due Date Finish Date Status Lead Person Reference
1. Add image capabilities to nodes (change "Audio URL" to "Image URL") START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
2. Display images when nodes are clicked (User tool) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
3. Allow users to decide which nodes are visible in User Tool (Buildings, Roads, etc.) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
4. Create user guide START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
5. Allow nodes to have multiple levels (numbered PNGs) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
6. Add more node "types" such as Sporting arena, Field START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
7. User tool should color the edges the same as Admin Tool (red = non-handicap, blue = neutral, purple = road) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
8. Populate the database for Clemson prototype (one of the last tasks) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
9. Fix dijkstra's algorithm START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
10. Fix deleting nodes START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
11. Fix updating node info START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
12. Transfer Database from a MS SQL 2005 server to a MySql Server START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
13. Slim down Web Services by adding Stored Procedures START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
14. Add casadeing deletes to maintain referential integrity START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
15. Add functions and procedures to add, delete and edit nodes START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
16. Add functions and procedures to add, delete and edit users START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
17. Add functions and procedures to add, delete and edit adjacencys START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
18. Add functions and procedures to add, delete and edit maps START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
19. Make a very sophistcated database back up (multiple automated back ups with multiple redundency) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
20. Add triggers to clean up individual fields when the database is altered (IE when the user changes position change the users position on their user profile) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
21. Add security from the user tool to the web services START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
22. Add security from the Admin tool to the web services START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
23. Add security from the web services to the database START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
24. Impliment multiple user accounts with a portlet on the IIS server to log in START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference
25. Add a logging tool to see what users are requesting and when. (We could get a paper out of this for sure!) START DATE Due Date Done Date Open CAMPUS MAP MEMBER No Reference